History and time schedule
History:
- 1990: First attempt to obtain funding for an accelerator or light source in Spain.
- 1994: Staff is hired to prepare the conceptual design report of a 2.5 GeV light source.
- 1997: Conceptual design report is finished.
- 2002: Approval of the project by the Spanish and the Catalan Governments.
- 2003: Appointement of the General Director (Joan Bordas)
- 2003: Announcement of the positions for the heads of the 5 divisions.
- 2003: 1st user meeting at Menorca.
- 2004: 2nd user meeting in Malaga.
- 2004: Redesign of the storage ring.
- 2004: Geotechnical studies on the site.
- 2005: Site conditioning.
- 2006: Start building construction.
- 2007: Linac installation.
Time schedule:
- 2008: Booster and storage ring installation.
- 2009: Commissioning.
- 2010: Users Operation with 7 beamlines.
|