Painting of the enclosures, cable trays, electrical supplies, mechanical and PSS were installed in the following six months.

Following Site Acceptance Tests, SAT, the hutches were painted in- and out-side, cable trays were installed both in- and outside, electricity and mechanical services were fitted. This was followed by the installation of PSS hardware and finally in the summer 2009 the roof handrails were fitted. Below is shown the beam line infrastructure as it was September 2009.

 