BOREAS - Photos of the installation of the main beamline components

27/1/2010  

After a long travel by boat from Toyama's factory in Japan, the boxes containing all the main beamline components (PM/TM mirror chamber, monochromator, entrance and exit slits and various diagnostics elements) arrive at ALBA!

First the truck is unloaded ... 

opt1 opt2

 

opt3 opt4

 

... and then the boxes are transferred to the beamline

opt5 opt6

 

opt7 opt8

 

28/1/2010

View of the beamline waiting for the installation of the components

Optics hutch (view towards the front-end, with the base plates of the PM/TM chamber in the front)

 opt9

View along the beam direction, with the baseplates of the entrance slits in the foreground

opt10

Experimental hall

View of the monochromator base plates with the hutch in the background

opt11

View along the beam direction, with the base plates of the exit slits in the foreground

opt12

View from the top

opt13

8/2/2009 - 13/2/2009

First week of installation by Toyama!

Unpacking of the boxes

toy1 toy2 

toy4

Installation of the PM-TM chamber inside the optics hutch:

first the ion pump support

ipsuppm1 ipsuppm2 ipsuppm3

... then the ion pump ...

ippm1 ippm2 ippm3

and finally the mirror chamber flies as well!

pm1 pm2 
pm3 pm4

15/2/2010 - 27/2/2010

Second and third weeks of installation

Installation of the exit slits ...

xs1 xs2


... while, somewhere in the optics lab, the mirrors of the beamline are being qualified with the long trace profiler

optlab1 optlab2

29/2/2010 - 6/3/2010

Fourth week of installation

Almost everything installed apart from the monochromator!

week4_1 week4_2

The entrance slit completes the hutch

es1 es2

8/3/2010 - 21/3/2010

Fifth and sixth weeks of installation

The monochromator goes to its position ...

mono1 mono2

mono3 mono4

... while outside ...

neve3 neve2


22/3/2010-24/3/2010

Last days of mechanical installation. The monochromator is left ready for bakeout.


27/4/2010-14/5/2010

Installation of the optical elements PM, TM, SM1, SM2 and LEG inside the PM-TM and the monochromator chambers.